CANONICAL ENERGY PROFILE SOURCE CLASSES KEPT APART
ENERGY ORGANIZATION / US-EIA860M-67735
Matrix Renewables
U.S. EIA scheduled generating entity
Matrix Renewables: 1 plants and 21.6 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.
Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
California
EIA schedule release
Aug 26, 2026
Identity and evidence classes.
Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.
Cloud Draw energy ID
us-eia860m:67735
EIA scheduled entity ID
67735
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2
Scheduled generating projects.
June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.
Scheduled plants
1
Scheduled units
1
Plant producer classes
IPP
Total net summer
21.6 MW
Generation
0 MW
Storage power
21.6 MW
Construction / complete
21.6 MW
Earlier stage
0 MW
Schedule window
2026-07 → 2026-07
EIA plant 69806CA
Gaskell West Storage 1, LLC
21.6 MW net summer0 MW generation · 21.6 MW storage power
21.6 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · GWBS1
Nameplate
21.6 MW
Technology
Batteries
Schedule
2026-07 → 2026-07
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.