Skip to profile facts
CLOUDDRAW

CANONICAL ENERGY PROFILE
SOURCE CLASSES KEPT APART

ENERGY ORGANIZATION / US-EIA860M-67585

Maricopa Solar

U.S. EIA scheduled generating entity

Maricopa Solar: 1 plants and 1,100 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.

Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
Arizona
EIA schedule release
Aug 26, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
us-eia860m:67585
EIA scheduled entity ID
67585
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2

Scheduled generating projects.

June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.

Scheduled plants
1
Scheduled units
2
Plant producer classes
IPP
Total net summer
1,100 MW
Generation
550 MW
Storage power
550 MW
Construction / complete
1,100 MW
Earlier stage
0 MW
Schedule window
2026-092026-09
EIA plant 69684AZ

Maricopa Solar

  • 1,100 MW net summer550 MW generation · 550 MW storage power
  • 1,100 MW construction / complete0 MW earlier stage · overlapping status axis
Units
2 · 70124, 70125
Nameplate
1,100 MW
Technology
Batteries · Solar Photovoltaic
Schedule
2026-092026-09

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗