Fremont Solar, LLC

U.S. EIA scheduled generating entity

Fremont Solar, LLC: 1 plants and 297 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.

Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
Utah
EIA schedule release
Aug 26, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
us-eia860m:66616
EIA scheduled entity ID
66616
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2

Scheduled generating projects.

June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.

Scheduled plants
1
Scheduled units
2
Plant producer classes
IPP
Total net summer
297 MW
Generation
99 MW
Storage power
198 MW
Construction / complete
297 MW
Earlier stage
0 MW
Schedule window
2027-062027-06
EIA plant 68153UT

Fremont Solar

  • 297 MW net summer99 MW generation · 198 MW storage power
  • 297 MW construction / complete0 MW earlier stage · overlapping status axis
Units
2 · BA1, PV1
Nameplate
297 MW
Technology
Batteries · Solar Photovoltaic
Schedule
2027-062027-06

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.