CANONICAL ENERGY PROFILE
SOURCE CLASSES KEPT APART

ENERGY ORGANIZATION / US-EIA860M-66571

Clenera DevCo LLC

U.S. EIA scheduled generating entity

Clenera DevCo LLC: 3 plants and 1,666 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.

Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
Arizona · California · Idaho
EIA schedule release
Aug 26, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
us-eia860m:66571
EIA scheduled entity ID
66571
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2

Scheduled generating projects.

June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.

Scheduled plants
3
Scheduled units
6
Plant producer classes
IPP
Total net summer
1,666 MW
Generation
919 MW
Storage power
747 MW
Construction / complete
516 MW
Earlier stage
1,150 MW
Schedule window
2026-122027-06
EIA plant 69060AZ

Snowflake A Solar and BESS

  • 950 MW net summer475 MW generation · 475 MW storage power
  • 0 MW construction / complete950 MW earlier stage · overlapping status axis
Units
2 · SNFA, SNFBA
Nameplate
950 MW
Technology
Batteries · Solar Photovoltaic
Schedule
2027-062027-06

(L) Regulatory approvals pending. Not under construction

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68940CA

Country Acres Clean Power LLC

  • 516 MW net summer344 MW generation · 172 MW storage power
  • 516 MW construction / complete0 MW earlier stage · overlapping status axis
Units
2 · CABS, CAPV
Nameplate
516 MW
Technology
Batteries · Solar Photovoltaic
Schedule
2026-122026-12

(U) Under construction, less than or equal to 50 percent complete · (V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69059ID

Crimson Orchard Solar and BESS

  • 200 MW net summer100 MW generation · 100 MW storage power
  • 0 MW construction / complete200 MW earlier stage · overlapping status axis
Units
2 · COBA, COPV
Nameplate
200 MW
Technology
Batteries · Solar Photovoltaic
Schedule
2027-042027-04

(L) Regulatory approvals pending. Not under construction

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗