Skip to profile facts
CLOUDDRAW

CANONICAL ENERGY PROFILE
SOURCE CLASSES KEPT APART

ENERGY ORGANIZATION / US-EIA860M-65869

Prologis Logistics Services Incorporated

U.S. EIA scheduled generating entity

Prologis Logistics Services Incorporated: 35 plants and 55.7 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.

Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
California · Illinois
EIA schedule release
Aug 26, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
us-eia860m:65869
EIA scheduled entity ID
65869
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2

Scheduled generating projects.

June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.

Scheduled plants
35
Scheduled units
36
Plant producer classes
IPP
Total net summer
55.7 MW
Generation
52.8 MW
Storage power
2.9 MW
Construction / complete
55.7 MW
Earlier stage
0 MW
Schedule window
2026-072027-05
EIA plant 70012CA

Redlands DC 9 - sline609

  • 5 MW net summer2.6 MW generation · 2.4 MW storage power
  • 5 MW construction / complete0 MW earlier stage · overlapping status axis
Units
2 · BA609, IN609
Nameplate
5 MW
Technology
Batteries · Solar Photovoltaic
Schedule
2026-092026-09

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68140IL

Melrose Park 2-SLCHI547

  • 3 MW net summer3 MW generation · 0 MW storage power
  • 3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH547
Nameplate
3 MW
Technology
Solar Photovoltaic
Schedule
2026-102026-10

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68144IL

Northlake 5-SLCHI305

  • 2.5 MW net summer2.5 MW generation · 0 MW storage power
  • 2.5 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH305
Nameplate
2.5 MW
Technology
Solar Photovoltaic
Schedule
2026-122026-12

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68139IL

McCook 2-SLCHI102

  • 2 MW net summer2 MW generation · 0 MW storage power
  • 2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH102
Nameplate
2 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68119IL

Aurora 7-SLCHI307

  • 1.9 MW net summer1.9 MW generation · 0 MW storage power
  • 1.9 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH307
Nameplate
1.9 MW
Technology
Solar Photovoltaic
Schedule
2027-042027-04

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68122IL

Bensenville 2-SLCHI526

  • 1.9 MW net summer1.9 MW generation · 0 MW storage power
  • 1.9 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH526
Nameplate
1.9 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68129IL

Cicero 3-SLCHI603

  • 1.9 MW net summer1.9 MW generation · 0 MW storage power
  • 1.9 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH603
Nameplate
1.9 MW
Technology
Solar Photovoltaic
Schedule
2027-042027-04

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68138IL

Internationale Ctr 11-SLCHI321

  • 1.8 MW net summer1.8 MW generation · 0 MW storage power
  • 1.8 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH321
Nameplate
1.8 MW
Technology
Solar Photovoltaic
Schedule
2027-032027-03

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68127IL

Bensenville Ind Park 4-SLCHI424

  • 1.7 MW net summer1.7 MW generation · 0 MW storage power
  • 1.7 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH424
Nameplate
1.7 MW
Technology
Solar Photovoltaic
Schedule
2026-102026-10

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68132IL

Elk Grove 1-SLCHI701

  • 1.7 MW net summer1.7 MW generation · 0 MW storage power
  • 1.7 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH701
Nameplate
1.7 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68118IL

Addison 11-SLCHI404

  • 1.6 MW net summer1.6 MW generation · 0 MW storage power
  • 1.6 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH404
Nameplate
1.6 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68130IL

Des Plaines 11-SLCHI211

  • 1.6 MW net summer1.6 MW generation · 0 MW storage power
  • 1.6 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH211
Nameplate
1.6 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68141IL

Northlake 2-SLCHI302

  • 1.6 MW net summer1.6 MW generation · 0 MW storage power
  • 1.6 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH302
Nameplate
1.6 MW
Technology
Solar Photovoltaic
Schedule
2026-112026-11

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68142IL

Northlake 3-SLCHI303

  • 1.6 MW net summer1.6 MW generation · 0 MW storage power
  • 1.6 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH303
Nameplate
1.6 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 70095CA

Perris DC 5 - sline015

  • 1.6 MW net summer1.6 MW generation · 0 MW storage power
  • 1.6 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · IN015
Nameplate
1.6 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68120IL

Bensenville 13-SLCHI513

  • 1.4 MW net summer1.4 MW generation · 0 MW storage power
  • 1.4 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH513
Nameplate
1.4 MW
Technology
Solar Photovoltaic
Schedule
2026-102026-10

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68133IL

Elk Grove 51-SLCHI151

  • 1.4 MW net summer1.4 MW generation · 0 MW storage power
  • 1.4 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH151
Nameplate
1.4 MW
Technology
Solar Photovoltaic
Schedule
2027-022027-02

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68143IL

Northlake 4-SLCHI304

  • 1.4 MW net summer1.4 MW generation · 0 MW storage power
  • 1.4 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH304
Nameplate
1.4 MW
Technology
Solar Photovoltaic
Schedule
2026-122026-12

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69891CA

Torrance Dis Ctr 2 - SLLAX100

  • 1.4 MW net summer1.4 MW generation · 0 MW storage power
  • 1.4 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LA100
Nameplate
1.4 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68793CA

Bandini - SLLAX710

  • 1.3 MW net summer1.3 MW generation · 0 MW storage power
  • 1.3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LA710
Nameplate
1.3 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68121IL

Bensenville 14-SLCHI414

  • 1.3 MW net summer1.3 MW generation · 0 MW storage power
  • 1.3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH414
Nameplate
1.3 MW
Technology
Solar Photovoltaic
Schedule
2027-042027-04

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68790CA

Dominguez - SLLAX512

  • 1.3 MW net summer1.3 MW generation · 0 MW storage power
  • 1.3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LA512
Nameplate
1.3 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68792CA

Fordyce - SLLAX680

  • 1.3 MW net summer1.3 MW generation · 0 MW storage power
  • 1.3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LA680
Nameplate
1.3 MW
Technology
Solar Photovoltaic
Schedule
2027-032027-03

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68137IL

Glendale Heights 10-SLCHI910

  • 1.3 MW net summer1.3 MW generation · 0 MW storage power
  • 1.3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH910
Nameplate
1.3 MW
Technology
Solar Photovoltaic
Schedule
2027-022027-02

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68237CA

South Bay Dis Ctr 20-SLLAX512

  • 1.3 MW net summer1.3 MW generation · 0 MW storage power
  • 1.3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LA512
Nameplate
1.3 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68236CA

South Bay Dis Ctr 6-SLLAX680

  • 1.3 MW net summer1.3 MW generation · 0 MW storage power
  • 1.3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LA680
Nameplate
1.3 MW
Technology
Solar Photovoltaic
Schedule
2026-122026-12

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68123IL

Bensenville Ind Park 10-SLCHI410

  • 1.2 MW net summer1.2 MW generation · 0 MW storage power
  • 1.2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH410
Nameplate
1.2 MW
Technology
Solar Photovoltaic
Schedule
2027-012027-01

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68124IL

Bensenville Ind Park 11

  • 1.2 MW net summer1.2 MW generation · 0 MW storage power
  • 1.2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH411
Nameplate
1.2 MW
Technology
Solar Photovoltaic
Schedule
2026-122026-12

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68238CA

Commerce Distribution Center 4-SLLAX113

  • 1.2 MW net summer1.2 MW generation · 0 MW storage power
  • 1.2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LA113
Nameplate
1.2 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68135IL

Franklin Park 2-SLCHI802

  • 1.2 MW net summer1.2 MW generation · 0 MW storage power
  • 1.2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH802
Nameplate
1.2 MW
Technology
Solar Photovoltaic
Schedule
2026-092026-09

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68789CA

South Bay Dis Ctr 12 - SLLAX104

  • 1.2 MW net summer1.2 MW generation · 0 MW storage power
  • 1.2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LA104
Nameplate
1.2 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68126IL

Bensenville Ind Park 2-SLCHI402

  • 1.1 MW net summer1.1 MW generation · 0 MW storage power
  • 1.1 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CH402
Nameplate
1.1 MW
Technology
Solar Photovoltaic
Schedule
2026-102026-10

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69609CA

San Leandro 10 - sleba702

  • 1 MW net summer1 MW generation · 0 MW storage power
  • 1 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · EB702
Nameplate
1 MW
Technology
Solar Photovoltaic
Schedule
2027-012027-01

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69786CA

Stockton 9 - slcva209

  • 1 MW net summer1 MW generation · 0 MW storage power
  • 1 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CV209
Nameplate
1 MW
Technology
Solar Photovoltaic
Schedule
2026-092026-09

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68235IL

Romeoville 34 - SLCHI234 - BSCHI234

  • 0.5 MW net summer0 MW generation · 0.5 MW storage power
  • 0.5 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · C34BB
Nameplate
0.5 MW
Technology
Batteries
Schedule
2027-052027-05

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗