Urban Grid Solar

U.S. EIA scheduled generating entity

Urban Grid Solar: 3 plants and 290 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.

Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
Alabama · Maryland · Pennsylvania
EIA schedule release
Aug 26, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
us-eia860m:65777
EIA scheduled entity ID
65777
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2

Scheduled generating projects.

June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.

Scheduled plants
3
Scheduled units
3
Plant producer classes
IPP
Total net summer
290 MW
Generation
290 MW
Storage power
0 MW
Construction / complete
55.8 MW
Earlier stage
234.2 MW
Schedule window
2026-072027-06
EIA plant 66852AL

Hillsboro Solar 3

  • 200 MW net summer200 MW generation · 0 MW storage power
  • 0 MW construction / complete200 MW earlier stage · overlapping status axis
Units
1 · HILL3
Nameplate
200 MW
Technology
Solar Photovoltaic
Schedule
2027-052027-05

(L) Regulatory approvals pending. Not under construction

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 66843MD

Morgnec Solar

  • 55.8 MW net summer55.8 MW generation · 0 MW storage power
  • 55.8 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · MORG1
Nameplate
55.8 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 66850PA

Beaver Creek Solar

  • 34.2 MW net summer34.2 MW generation · 0 MW storage power
  • 0 MW construction / complete34.2 MW earlier stage · overlapping status axis
Units
1 · BEAC1
Nameplate
34.2 MW
Technology
Solar Photovoltaic
Schedule
2027-062027-06

(L) Regulatory approvals pending. Not under construction

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗