AES Clean Energy

U.S. EIA scheduled generating entity

AES Clean Energy: 8 plants and 459.2 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.

Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
California · Illinois · New York · North Carolina · Texas
EIA schedule release
Aug 26, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
us-eia860m:64904
EIA scheduled entity ID
64904
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2

Scheduled generating projects.

June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.

Scheduled plants
8
Scheduled units
9
Plant producer classes
IPP
Total net summer
459.2 MW
Generation
344.8 MW
Storage power
114.4 MW
Construction / complete
459.2 MW
Earlier stage
0 MW
Schedule window
2026-072027-04
EIA plant 64349TX

Armadillo Solar Center

  • 175 MW net summer175 MW generation · 0 MW storage power
  • 175 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · 6666
Nameplate
175 MW
Technology
Solar Photovoltaic
Schedule
2027-042027-04

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 70109CA

Jasmine

  • 134.4 MW net summer70 MW generation · 64.4 MW storage power
  • 134.4 MW construction / complete0 MW earlier stage · overlapping status axis
Units
2 · JASBE, JASMI
Nameplate
134.4 MW
Technology
Batteries · Solar Photovoltaic
Schedule
2026-122027-04

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69197NC

Halifax County Solar

  • 80 MW net summer80 MW generation · 0 MW storage power
  • 80 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · HALIF
Nameplate
80 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69964CA

Baldy Mesa Storage

  • 50 MW net summer0 MW generation · 50 MW storage power
  • 50 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · BALBE
Nameplate
50 MW
Technology
Batteries
Schedule
2026-092026-09

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 70177IL

Allen CSG

  • 5 MW net summer5 MW generation · 0 MW storage power
  • 5 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · ALLEN
Nameplate
5 MW
Technology
Solar Photovoltaic
Schedule
2026-092026-09

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 70176IL

Kieser

  • 5 MW net summer5 MW generation · 0 MW storage power
  • 5 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · KIESE
Nameplate
5 MW
Technology
Solar Photovoltaic
Schedule
2026-092026-09

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68389NY

AES Glengarry Farms Solar CSG

  • 4.9 MW net summer4.9 MW generation · 0 MW storage power
  • 4.9 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · GLENG
Nameplate
5 MW
Technology
Solar Photovoltaic
Schedule
2026-092026-09

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 68388NY

AES Rt 5 Solar CSG

  • 4.9 MW net summer4.9 MW generation · 0 MW storage power
  • 4.9 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · RT5SS
Nameplate
5 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗