ENERGY ORGANIZATION / US-EIA860M-62759

Geronimo Power

U.S. EIA scheduled generating entity

Geronimo Power: 3 plants and 525 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.

Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
Illinois · Michigan · Wisconsin
EIA schedule release
Aug 26, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
us-eia860m:62759
EIA scheduled entity ID
62759
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2

Scheduled generating projects.

June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.

Scheduled plants
3
Scheduled units
3
Plant producer classes
IPP
Total net summer
525 MW
Generation
525 MW
Storage power
0 MW
Construction / complete
275 MW
Earlier stage
250 MW
Schedule window
2026-082027-05
EIA plant 69887WI

Portage Solar, LLC

  • 250 MW net summer250 MW generation · 0 MW storage power
  • 0 MW construction / complete250 MW earlier stage · overlapping status axis
Units
1 · PRTGS
Nameplate
250 MW
Technology
Solar Photovoltaic
Schedule
2027-032027-03

(T) Regulatory approvals received. Not under construction

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69874IL

Bee Hollow Solar, LLC

  • 150 MW net summer150 MW generation · 0 MW storage power
  • 150 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · BHSF
Nameplate
150 MW
Technology
Solar Photovoltaic
Schedule
2027-052027-05

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69647MI

Jackson County Solar, LLC

  • 125 MW net summer125 MW generation · 0 MW storage power
  • 125 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · JCKSN
Nameplate
125 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗