Cypress Creek Renewables
U.S. EIA scheduled generating entity
Cypress Creek Renewables: 3 plants and 404.9 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.
Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
Colorado · North Carolina · Texas
EIA schedule release
Aug 26, 2026
Identity and evidence classes.
Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.
Cloud Draw energy ID
us-eia860m:61060
EIA scheduled entity ID
61060
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2
Scheduled generating projects.
June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.
Scheduled plants
3
Scheduled units
4
Plant producer classes
IPP
Total net summer
404.9 MW
Generation
154.9 MW
Storage power
250 MW
Construction / complete
324.9 MW
Earlier stage
80 MW
Schedule window
2026-08 → 2027-05
EIA plant 67654TX
Destiny Storage
200 MW net summer0 MW generation · 200 MW storage power
200 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · DESTS
Nameplate
200 MW
Technology
Batteries
Schedule
2026-08 → 2026-08
(U) Under construction, less than or equal to 50 percent complete