Standard Solar

U.S. EIA scheduled generating entity

Standard Solar: 13 plants and 36.1 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.

Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
Delaware · Illinois · Minnesota · New Jersey · New Mexico · New York
EIA schedule release
Aug 26, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
us-eia860m:60531
EIA scheduled entity ID
60531
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2

Scheduled generating projects.

June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.

Scheduled plants
13
Scheduled units
14
Plant producer classes
IPP
Total net summer
36.1 MW
Generation
33.6 MW
Storage power
2.5 MW
Construction / complete
36.1 MW
Earlier stage
0 MW
Schedule window
2026-072027-01
EIA plant 70295IL

NL IL Lake

  • 5 MW net summer5 MW generation · 0 MW storage power
  • 5 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LAKE
Nameplate
5 MW
Technology
Solar Photovoltaic
Schedule
2026-092026-09

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69592NY

NL NY- Pulaski

  • 5 MW net summer2.5 MW generation · 2.5 MW storage power
  • 5 MW construction / complete0 MW earlier stage · overlapping status axis
Units
2 · PSKBS, PSKPV
Nameplate
5 MW
Technology
Batteries · Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69558NM

Pluma - SLT Grant

  • 4.8 MW net summer4.8 MW generation · 0 MW storage power
  • 4.8 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · GRANT
Nameplate
4.8 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 70228IL

AC IL - Lockport West

  • 3.4 MW net summer3.4 MW generation · 0 MW storage power
  • 3.4 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LOCKW
Nameplate
3.4 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 70227IL

AC IL - Lockport East

  • 3.1 MW net summer3.1 MW generation · 0 MW storage power
  • 3.1 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · LOCKE
Nameplate
3.1 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69560DE

Sunrise Magnolia DE

  • 3 MW net summer3 MW generation · 0 MW storage power
  • 3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · MAGNO
Nameplate
3 MW
Technology
Solar Photovoltaic
Schedule
2027-012027-01

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69555NJ

Citrine NJ - West Pkwy

  • 2.3 MW net summer2.3 MW generation · 0 MW storage power
  • 2.3 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · WESTP
Nameplate
2.3 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 70294IL

NL IL 2700 East

  • 2 MW net summer2 MW generation · 0 MW storage power
  • 2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · EAST
Nameplate
2 MW
Technology
Solar Photovoltaic
Schedule
2026-102026-10

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 70046IL

OER IL - Groundhog

  • 2 MW net summer2 MW generation · 0 MW storage power
  • 2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · GNDHG
Nameplate
2 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69554NJ

BPL NJ - Belmont

  • 1.8 MW net summer1.8 MW generation · 0 MW storage power
  • 1.8 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · BELMO
Nameplate
1.8 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69791NJ

BPL NJ - Union Distribution Center

  • 1.5 MW net summer1.5 MW generation · 0 MW storage power
  • 1.5 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · NJUDC
Nameplate
1.5 MW
Technology
Solar Photovoltaic
Schedule
2026-082026-08

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69790NJ

Elizabeth Metropolitan Logistics Center

  • 1.2 MW net summer1.2 MW generation · 0 MW storage power
  • 1.2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · EZMLC
Nameplate
1.2 MW
Technology
Solar Photovoltaic
Schedule
2026-072026-07

(TS) Construction complete, but not yet in commercial operation

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 69305MN

Enterprise MN - Fitzthum

  • 1 MW net summer1 MW generation · 0 MW storage power
  • 1 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · FITZH
Nameplate
1 MW
Technology
Solar Photovoltaic
Schedule
2026-092026-09

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.