Dominion Energy Inc.

U.S. EIA scheduled generating entity

Dominion Energy Inc.: 4 plants and 2,927.2 MW in EIA's preliminary 2026-07–2027-06 scheduled-additions window. This is not actual production or a data-center contract.

Source-established role / class
Generator / project developer
Country / scope
United States
Published geography
Virginia
EIA schedule release
Aug 26, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
us-eia860m:5248
EIA scheduled entity ID
5248
Record classes
U.S. EIA scheduled generating entity
Source-established role / class
Generator / project developer
Original-source routes
2

Scheduled generating projects.

June 2026 EIA schedule for 2026-07 through 2027-06. Generation and storage form one technology split; construction and earlier-stage status form a second overlapping split. They are not added across axes.

Scheduled plants
4
Scheduled units
5
Plant producer classes
Electric Utility
Total net summer
2,927.2 MW
Generation
2,877.2 MW
Storage power
50 MW
Construction / complete
2,927.2 MW
Earlier stage
0 MW
Schedule window
2026-072027-06
EIA plant 64550VA

Coastal Virginia Offshore Wind (CVOW) Commercial Project

  • 2,640 MW net summer2,640 MW generation · 0 MW storage power
  • 2,640 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CVOWC
Nameplate
2,640 MW
Technology
Offshore Wind Turbine
Schedule
2027-012027-01

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 65043VA

Dulles Solar and Storage

  • 150 MW net summer100 MW generation · 50 MW storage power
  • 150 MW construction / complete0 MW earlier stage · overlapping status axis
Units
2 · DUSO, DUST
Nameplate
150 MW
Technology
Batteries · Solar Photovoltaic
Schedule
2026-072026-09

(V) Under construction, more than 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 66315VA

Clover Creek Solar

  • 77.2 MW net summer77.2 MW generation · 0 MW storage power
  • 77.2 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · CCSO
Nameplate
77.2 MW
Technology
Solar Photovoltaic
Schedule
2027-062027-06

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗
EIA plant 66313VA

Moon Corner Solar

  • 60 MW net summer60 MW generation · 0 MW storage power
  • 60 MW construction / complete0 MW earlier stage · overlapping status axis
Units
1 · MOCO
Nameplate
60 MW
Technology
Solar Photovoltaic
Schedule
2026-092026-09

(U) Under construction, less than or equal to 50 percent complete

Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.

EIA Table 6.5 workbook ↗