EIA plant 66968IN
Blackford Wind
- 200 MW net summer200 MW generation · 0 MW storage power
- 200 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · BFW00
- Nameplate
- 200 MW
- Technology
- Onshore Wind Turbine
- Schedule
- 2026-12 → 2026-12
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 68089OK
Twelvemile Solar 3
- 200 MW net summer200 MW generation · 0 MW storage power
- 200 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · TS03
- Nameplate
- 200 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2026-12 → 2026-12
(U) Under construction, less than or equal to 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 66960IN
Blackford Solar
- 150 MW net summer150 MW generation · 0 MW storage power
- 150 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · BLKSL
- Nameplate
- 150 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2026-10 → 2026-10
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 68086OH
South Branch Solar
- 115 MW net summer115 MW generation · 0 MW storage power
- 0 MW construction / complete115 MW earlier stage · overlapping status axis
- Units
- 1 · SBS
- Nameplate
- 115 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2027-06 → 2027-06
(L) Regulatory approvals pending. Not under construction
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 68006OK
Mayes County Solar
- 101.5 MW net summer101.5 MW generation · 0 MW storage power
- 101.5 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · MYS
- Nameplate
- 101.5 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2026-09 → 2026-09
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 68009OK
Saltbranch 2
- 73 MW net summer73 MW generation · 0 MW storage power
- 73 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · SB12
- Nameplate
- 73 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2026-07 → 2026-07
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 68007OK
Saltbranch Solar 1
- 73 MW net summer73 MW generation · 0 MW storage power
- 73 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · SLTB1
- Nameplate
- 73 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2026-08 → 2026-08
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗