EIA plant 69778AZ
Hashknife Energy Center LLC
- 550 MW net summer275 MW generation · 275 MW storage power
- 550 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 2 · HK1SO, HK1ST
- Nameplate
- 550 MW
- Technology
- Batteries · Solar Photovoltaic
- Schedule
- 2026-09 → 2026-09
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 69779AZ
Hashknife Energy Center II LLC
- 400 MW net summer200 MW generation · 200 MW storage power
- 400 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 2 · HK2SO, HK2ST
- Nameplate
- 400 MW
- Technology
- Batteries · Solar Photovoltaic
- Schedule
- 2027-03 → 2027-03
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 62954NY
Alle-Catt Wind Energy LLC
- 340 MW net summer340 MW generation · 0 MW storage power
- 340 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · GEN1
- Nameplate
- 340 MW
- Technology
- Onshore Wind Turbine
- Schedule
- 2026-12 → 2026-12
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 69479WI
Koshkonong Solar Energy Center LLC
- 300 MW net summer300 MW generation · 0 MW storage power
- 300 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · KSHKS
- Nameplate
- 300 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2026-12 → 2026-12
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 69478TX
Lazbuddie Wind Energy LLC
- 265 MW net summer265 MW generation · 0 MW storage power
- 265 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · LZBDE
- Nameplate
- 265 MW
- Technology
- Onshore Wind Turbine
- Schedule
- 2026-07 → 2026-07
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 63028NM
Tip Top Solar Energy Center LLC
- 220 MW net summer220 MW generation · 0 MW storage power
- 220 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · GEN1
- Nameplate
- 220 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2026-12 → 2026-12
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 69477OH
Pleasant Prairie Solar Energy LLC
- 200 MW net summer200 MW generation · 0 MW storage power
- 200 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · PLSNT
- Nameplate
- 200 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2026-12 → 2026-12
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗EIA plant 69111IN
Trade Post Solar
- 200 MW net summer200 MW generation · 0 MW storage power
- 200 MW construction / complete0 MW earlier stage · overlapping status axis
- Units
- 1 · TRADE
- Nameplate
- 200 MW
- Technology
- Solar Photovoltaic
- Schedule
- 2026-07 → 2026-07
(V) Under construction, more than 50 percent complete
Preliminary scheduled capacity is not guaranteed completion, expected MWh, a data-center allocation, or proof of a power contract.
EIA Table 6.5 workbook ↗