ENERGY ORGANIZATION / BLOOM-ENERGY

Bloom Energy

Also indexed as Bloom

Source-linked data-center relationship

Bloom Energy: source-linked data-center energy relationships, projects, capacity stages, roles, and original documents in Cloud Draw.

Source-established role / class
Power technology provider
Country / scope
United States
Published geography
Multiple states
Evidence checked
Aug 31, 2026

Identity and evidence classes.

Official source identifiers join records when available. Similar labels, brands, establishments, subsidiaries, parents, and affiliates remain separate until a source establishes the relationship.

Cloud Draw energy ID
curated:bloom-energy-provider
Record classes
Source-linked data-center relationship
Source-established role / class
Power technology provider
Original-source routes
14

Data-center relationships and capacity facts.

Operating, construction, contracted, approved, framework, forecast, and manufacturing figures stay separate. Parent totals and included projects are marked so they are never counted twice.

under construction19 U.S. IBX data centers in six states

Equinix U.S. onsite fuel-cell portfolio

Equinix · Bloom supplies onsite solid-oxide fuel-cell systems across the sourced Equinix portfolio

  • ≈75 MW operatingOperating / deployed · portfolio nameplateApproximate operating portfolio nameplate reported by Bloom in February 2025.
  • ≈30 MW under constructionUnder construction · portfolio nameplateApproximate construction portfolio nameplate reported in the same release.
  • 100+ MW portfolio totalOperating / deployed · portfolio nameplateOverlapping portfolio total that includes the operating and construction figures above; it is not added again.
Status
Operating and under construction
Timeline
Portfolio exceeded 100 MW in February 2025
Technology
Solid-oxide fuel cells; feedstock is not stated in the cited release
Source date
Feb 20, 2025

Portfolio nameplate is not actual generation, facility draw, or a site-by-site allocation.

Bloom Energy · Equinix expansion
contractedUnited States; individual project sites are not listed in the release

Oracle U.S. AI infrastructure deployment

Oracle Cloud Infrastructure · Bloom supplies onsite fuel-cell systems under an expanded master services agreement

  • 1.2 GW initially contractedContracted / deploying · contract capacityBloom says deployment of the initial contracted capacity is underway.
  • Up to 2.8 GW master-agreement ceilingFramework ceiling / option · contract capacityThe 2.8 GW ceiling includes the initial 1.2 GW and must not be added to it.
Status
Initial capacity contracted; deployment underway
Timeline
Announced April 13, 2026; initial deployment continues into 2027
Technology
Solid-oxide fuel-cell systems
Source date
Apr 13, 2026

Contract capacity and a master-agreement ceiling are not completed production, actual MWh, or a disclosed facility-by-facility allocation.

Bloom Energy · Oracle expanded partnership
contractedAEP service territories; initial Ohio projects were later identified for AWS and Cologix

AEP customer-sited fuel-cell program

American Electric Power and large-load customers · AEP purchases Bloom systems for customer-sited, behind-the-meter generation

  • 100 MW initial purchaseContracted / deploying · contract capacityAEP reported acquiring 100 MW in its 2024 Form 10-K.
  • Option up to 1 GW totalFramework ceiling / option · contract capacityThe option includes the initial 100 MW and was stated with an end-of-2025 exercise window in the cited filing.
Status
Initial purchase agreement; larger option
Timeline
Agreement executed in the fourth quarter of 2024; exact current contracted total requires a newer filing
Technology
Solid-oxide fuel cells
Source date
Feb 27, 2025

The option is not an operating fleet, and the program does not identify actual generation or every customer project.

AEP 2024 Form 10-K · customer-sited fuel cells
approvedSanta Clara, California

Silicon Valley Power / AWS data-center agreement

Silicon Valley Power and Amazon Web Services · Municipal approval for an agreement using Bloom fuel cells at AWS data centers

  • 20 MW approved agreementPlanned / approved · contract capacityThe release reports municipal approval, not a current operating-output measurement.
Status
Municipal agreement approval reported
Timeline
Reported in Bloom second-quarter results on August 8, 2024
Technology
Solid-oxide fuel cells
Source date
Aug 8, 2024

Approval and agreement capacity do not prove commissioning, actual generation, or a facility meter reading.

Bloom Energy · Q2 2024 results
status refresh neededVolo, Illinois

CoreWeave / Chirisa Volo onsite project

CoreWeave and Chirisa Technology Parks · Bloom was selected to provide onsite fuel-cell generation for a CoreWeave deployment at a Chirisa-owned data center

    No public project MW was found in the attached source.

    Status
    Commissioning was scheduled; current completion not confirmed in this record
    Timeline
    July 2024 release targeted commissioning in Q3 2025
    Technology
    Solid-oxide fuel cells
    Source date
    Jul 16, 2024

    The cited release publishes no MW and its forward-looking commissioning date is not proof that the system entered service.

    Bloom Energy · CoreWeave partnership
    frameworkGlobal; individual financed projects are not listed

    Brookfield AI infrastructure financing framework

    Brookfield · Framework to finance rapid power projects for AI infrastructure using Bloom onsite power

      No public project MW was found in the attached source.

      Status
      Expanded financing framework
      Timeline
      Expanded from $5 billion to $25 billion on June 30, 2026
      Technology
      Bloom onsite fuel-cell platform
      Source date
      Jun 30, 2026

      A financing envelope is not MW, project approval, committed spend, construction, or electricity production.

      Bloom Energy · Brookfield expanded partnership
      under constructionUnited States; exact site not named in the announcement

      Nebius AI infrastructure onsite-power project

      Nebius · Bloom supplies onsite power for Nebius AI infrastructure

      • 328 MW planned installed capacityUnder construction · generation nameplateProject nameplate announced by Nebius; completion still requires a later operating source.
      Status
      Planned; expected to become operational during 2026
      Timeline
      Announced May 20, 2026 with an expected 2026 operating date
      Technology
      Solid-oxide fuel-cell systems
      Source date
      May 20, 2026

      Planned installed capacity is not current generation, actual MWh, or proof that the project entered service.

      Nebius · Bloom Energy partnership
      under constructionDoña Ana County, New Mexico

      Oracle / BorderPlex Project Jupiter

      Oracle and BorderPlex Digital Assets · Bloom fuel-cell systems are planned as onsite power for Oracle AI infrastructure at Project Jupiter

      • Up to 2.45 GW planned installed capacityUnder construction · generation nameplateProject design ceiling; it sits within the broader Oracle relationship and is not added to the 2.8 GW master-agreement ceiling.
      Status
      Construction moving forward; future installed capacity
      Timeline
      Oracle update published April 27, 2026
      Technology
      Solid-oxide fuel-cell systems
      Source date
      Apr 27, 2026

      Planned installed capacity is not operating generation or actual MWh. This project is a drill-down within the broader Oracle agreement.

      Oracle · Project Jupiter power announcement
      under constructionUnited States; individual sites and customers are not fully disclosed

      Brookfield behind-the-meter AI power projects

      Brookfield and unnamed U.S. hyperscaler customers · Brookfield finances and develops Bloom-powered behind-the-meter AI infrastructure projects

      • 55 MW completed projectOperating / deployed · portfolio nameplateCompleted project is included in the approximately 230 MW portfolio total.
      • ≈230 MW total under agreementsContracted / deploying · contract capacityPortfolio total includes the completed 55 MW and must not be added to it.
      Status
      One project reported complete; additional capacity under agreements
      Timeline
      Brookfield fourth-quarter 2025 unitholder update
      Technology
      Bloom onsite fuel-cell platform
      Source date
      Feb 6, 2026

      The customer and site list is incomplete, and contracted nameplate is not actual generation. This capacity is related to, but distinct from, the $25 billion financing ceiling.

      Brookfield Infrastructure · Q4 2025 letter
      approvedHilliard, Ohio

      AWS Scioto Darby Creek fuel-cell project

      Amazon Web Services and AEP Ohio · AEP Ohio plans customer-sited Bloom generation for an AWS data center

      • 72.9 MW approved projectPlanned / approved · generation nameplateThis project sits within the AEP program and initial 100 MW order; it is not additional to that program total.
      Status
      Approved; construction planned
      Timeline
      Approval reported September 2025; planned construction from early fall 2026 through early fall 2027
      Technology
      228 Bloom Energy Servers using natural gas
      Source date
      Sep 18, 2025

      Approval and planned construction are not operating production or actual MWh.

      AEP Ohio · Scioto Darby Creek project
      approvedJohnstown, Ohio

      Cologix Central Ohio fuel-cell project

      Cologix and AEP Ohio · AEP Ohio identifies Cologix as one of the first approved customer-sited Bloom projects

        No public project MW was found in the attached source.

        Status
        Approved project; exact MW not public in the attached record
        Timeline
        AEP Ohio approval announcement published June 5, 2025
        Technology
        Solid-oxide fuel cells using natural gas
        Source date
        Jun 5, 2025

        Do not infer Cologix capacity by subtracting the AWS project from AEP’s 100 MW initial order.

        AEP Ohio · PUCO approval announcement
        operatingBengaluru, India

        Nxtra Bengaluru onsite fuel-cell installation

        Nxtra by Airtel · Bloom fuel cells supply onsite power to an Nxtra data center

        • 0.5 MW installedOperating / deployed · generation nameplateInstalled nameplate; the source does not publish actual MWh generated.
        Status
        Installed and reported supplying power
        Timeline
        Bloom reported the installation operating in December 2022
        Technology
        Solid-oxide fuel cells
        Source date
        Dec 14, 2022

        Nxtra’s broader data-center expansion capacity is not Bloom generation and is not used here.

        Bloom Energy · Nxtra India deployment
        Provider benchmark2025-07-24

        Provider-reported data-center deployment

        • 400+ MW deployed worldwideThis global provider aggregate overlaps named projects and is not added to project-level capacity. It is deployed nameplate, not actual MWh generated.
        Bloom Energy · Oracle initial collaboration
        Provider benchmark2025-12-31

        Factory production-capacity target

        • ≈1 GW/year → 2 GW/year targetThis is manufacturing throughput and an end-of-2026 target—not installed project capacity, electricity generation, or data-center consumption.
        Bloom Energy 2025 Form 10-K