under construction19 U.S. IBX data centers in six states
Equinix U.S. onsite fuel-cell portfolio
Equinix · Bloom supplies onsite solid-oxide fuel-cell systems across the sourced Equinix portfolio
- ≈75 MW operatingOperating / deployed · portfolio nameplateApproximate operating portfolio nameplate reported by Bloom in February 2025.
- ≈30 MW under constructionUnder construction · portfolio nameplateApproximate construction portfolio nameplate reported in the same release.
- 100+ MW portfolio totalOperating / deployed · portfolio nameplateOverlapping portfolio total that includes the operating and construction figures above; it is not added again.
- Status
- Operating and under construction
- Timeline
- Portfolio exceeded 100 MW in February 2025
- Technology
- Solid-oxide fuel cells; feedstock is not stated in the cited release
- Source date
- Feb 20, 2025
Portfolio nameplate is not actual generation, facility draw, or a site-by-site allocation.
Bloom Energy · Equinix expansion ↗contractedUnited States; individual project sites are not listed in the release
Oracle U.S. AI infrastructure deployment
Oracle Cloud Infrastructure · Bloom supplies onsite fuel-cell systems under an expanded master services agreement
- 1.2 GW initially contractedContracted / deploying · contract capacityBloom says deployment of the initial contracted capacity is underway.
- Up to 2.8 GW master-agreement ceilingFramework ceiling / option · contract capacityThe 2.8 GW ceiling includes the initial 1.2 GW and must not be added to it.
- Status
- Initial capacity contracted; deployment underway
- Timeline
- Announced April 13, 2026; initial deployment continues into 2027
- Technology
- Solid-oxide fuel-cell systems
- Source date
- Apr 13, 2026
Contract capacity and a master-agreement ceiling are not completed production, actual MWh, or a disclosed facility-by-facility allocation.
Bloom Energy · Oracle expanded partnership ↗contractedAEP service territories; initial Ohio projects were later identified for AWS and Cologix
AEP customer-sited fuel-cell program
American Electric Power and large-load customers · AEP purchases Bloom systems for customer-sited, behind-the-meter generation
- 100 MW initial purchaseContracted / deploying · contract capacityAEP reported acquiring 100 MW in its 2024 Form 10-K.
- Option up to 1 GW totalFramework ceiling / option · contract capacityThe option includes the initial 100 MW and was stated with an end-of-2025 exercise window in the cited filing.
- Status
- Initial purchase agreement; larger option
- Timeline
- Agreement executed in the fourth quarter of 2024; exact current contracted total requires a newer filing
- Technology
- Solid-oxide fuel cells
- Source date
- Feb 27, 2025
The option is not an operating fleet, and the program does not identify actual generation or every customer project.
AEP 2024 Form 10-K · customer-sited fuel cells ↗approvedSanta Clara, California
Silicon Valley Power / AWS data-center agreement
Silicon Valley Power and Amazon Web Services · Municipal approval for an agreement using Bloom fuel cells at AWS data centers
- 20 MW approved agreementPlanned / approved · contract capacityThe release reports municipal approval, not a current operating-output measurement.
- Status
- Municipal agreement approval reported
- Timeline
- Reported in Bloom second-quarter results on August 8, 2024
- Technology
- Solid-oxide fuel cells
- Source date
- Aug 8, 2024
Approval and agreement capacity do not prove commissioning, actual generation, or a facility meter reading.
Bloom Energy · Q2 2024 results ↗status refresh neededVolo, Illinois
CoreWeave / Chirisa Volo onsite project
CoreWeave and Chirisa Technology Parks · Bloom was selected to provide onsite fuel-cell generation for a CoreWeave deployment at a Chirisa-owned data center
No public project MW was found in the attached source.
- Status
- Commissioning was scheduled; current completion not confirmed in this record
- Timeline
- July 2024 release targeted commissioning in Q3 2025
- Technology
- Solid-oxide fuel cells
- Source date
- Jul 16, 2024
The cited release publishes no MW and its forward-looking commissioning date is not proof that the system entered service.
Bloom Energy · CoreWeave partnership ↗frameworkGlobal; individual financed projects are not listed
Brookfield AI infrastructure financing framework
Brookfield · Framework to finance rapid power projects for AI infrastructure using Bloom onsite power
No public project MW was found in the attached source.
- Status
- Expanded financing framework
- Timeline
- Expanded from $5 billion to $25 billion on June 30, 2026
- Technology
- Bloom onsite fuel-cell platform
- Source date
- Jun 30, 2026
A financing envelope is not MW, project approval, committed spend, construction, or electricity production.
Bloom Energy · Brookfield expanded partnership ↗under constructionUnited States; exact site not named in the announcement
Nebius AI infrastructure onsite-power project
Nebius · Bloom supplies onsite power for Nebius AI infrastructure
- 328 MW planned installed capacityUnder construction · generation nameplateProject nameplate announced by Nebius; completion still requires a later operating source.
- Status
- Planned; expected to become operational during 2026
- Timeline
- Announced May 20, 2026 with an expected 2026 operating date
- Technology
- Solid-oxide fuel-cell systems
- Source date
- May 20, 2026
Planned installed capacity is not current generation, actual MWh, or proof that the project entered service.
Nebius · Bloom Energy partnership ↗under constructionDoña Ana County, New Mexico
Oracle / BorderPlex Project Jupiter
Oracle and BorderPlex Digital Assets · Bloom fuel-cell systems are planned as onsite power for Oracle AI infrastructure at Project Jupiter
- Up to 2.45 GW planned installed capacityUnder construction · generation nameplateProject design ceiling; it sits within the broader Oracle relationship and is not added to the 2.8 GW master-agreement ceiling.
- Status
- Construction moving forward; future installed capacity
- Timeline
- Oracle update published April 27, 2026
- Technology
- Solid-oxide fuel-cell systems
- Source date
- Apr 27, 2026
Planned installed capacity is not operating generation or actual MWh. This project is a drill-down within the broader Oracle agreement.
Oracle · Project Jupiter power announcement ↗under constructionUnited States; individual sites and customers are not fully disclosed
Brookfield behind-the-meter AI power projects
Brookfield and unnamed U.S. hyperscaler customers · Brookfield finances and develops Bloom-powered behind-the-meter AI infrastructure projects
- 55 MW completed projectOperating / deployed · portfolio nameplateCompleted project is included in the approximately 230 MW portfolio total.
- ≈230 MW total under agreementsContracted / deploying · contract capacityPortfolio total includes the completed 55 MW and must not be added to it.
- Status
- One project reported complete; additional capacity under agreements
- Timeline
- Brookfield fourth-quarter 2025 unitholder update
- Technology
- Bloom onsite fuel-cell platform
- Source date
- Feb 6, 2026
The customer and site list is incomplete, and contracted nameplate is not actual generation. This capacity is related to, but distinct from, the $25 billion financing ceiling.
Brookfield Infrastructure · Q4 2025 letter ↗approvedHilliard, Ohio
AWS Scioto Darby Creek fuel-cell project
Amazon Web Services and AEP Ohio · AEP Ohio plans customer-sited Bloom generation for an AWS data center
- 72.9 MW approved projectPlanned / approved · generation nameplateThis project sits within the AEP program and initial 100 MW order; it is not additional to that program total.
- Status
- Approved; construction planned
- Timeline
- Approval reported September 2025; planned construction from early fall 2026 through early fall 2027
- Technology
- 228 Bloom Energy Servers using natural gas
- Source date
- Sep 18, 2025
Approval and planned construction are not operating production or actual MWh.
AEP Ohio · Scioto Darby Creek project ↗approvedJohnstown, Ohio
Cologix Central Ohio fuel-cell project
Cologix and AEP Ohio · AEP Ohio identifies Cologix as one of the first approved customer-sited Bloom projects
No public project MW was found in the attached source.
- Status
- Approved project; exact MW not public in the attached record
- Timeline
- AEP Ohio approval announcement published June 5, 2025
- Technology
- Solid-oxide fuel cells using natural gas
- Source date
- Jun 5, 2025
Do not infer Cologix capacity by subtracting the AWS project from AEP’s 100 MW initial order.
AEP Ohio · PUCO approval announcement ↗operatingBengaluru, India
Nxtra Bengaluru onsite fuel-cell installation
Nxtra by Airtel · Bloom fuel cells supply onsite power to an Nxtra data center
- 0.5 MW installedOperating / deployed · generation nameplateInstalled nameplate; the source does not publish actual MWh generated.
- Status
- Installed and reported supplying power
- Timeline
- Bloom reported the installation operating in December 2022
- Technology
- Solid-oxide fuel cells
- Source date
- Dec 14, 2022
Nxtra’s broader data-center expansion capacity is not Bloom generation and is not used here.
Bloom Energy · Nxtra India deployment ↗Provider benchmark2025-07-24
Provider-reported data-center deployment
- 400+ MW deployed worldwideThis global provider aggregate overlaps named projects and is not added to project-level capacity. It is deployed nameplate, not actual MWh generated.
Bloom Energy · Oracle initial collaboration ↗Provider benchmark2025-12-31
Factory production-capacity target
- ≈1 GW/year → 2 GW/year targetThis is manufacturing throughput and an end-of-2026 target—not installed project capacity, electricity generation, or data-center consumption.
Bloom Energy 2025 Form 10-K ↗